Facilities Enhancement Team Projects Currently in progress


John Lentz

2:05 pm, November 13th, 2007

This thread is to show the work that is being done with the Facilities Enhancement Team


John Lentz

2:09 pm, November 13th, 2007

Boilers:

We decided to hold off on the generous gift of new ultra efficient boilers by Dale Howey at this time as the costs were spiraling out of control too quickly for the church's portion. When we left off it would be $42,000, and that did not include the necessary upgrades to the system that we need to implement anyway.

 We are focusing this winter on getting our current system to optimal efficiency and have already found many areas that we are improving upon, and have a plan for continued improvement.



John Lentz

3:58 pm, November 13th, 2007

The Foote Room Carpet and walls

We are currently bidding out the work to repaint the walls and get new carpet in the Foote Room. Julia McFadden and Mary Barret are working closely with Barbara Hubbard and John Lentz on this project.